CHALLENGE · SOLUTION · RESULTS
Project Overview
Challenge
The waste-heat power circulating water system had a high heat load and fast scaling and microbial growth. Heavy chemical dosing was required, the concentration factor was hard to raise, and makeup / blowdown costs remained high.
Solution
Two high-capacity GJQ-S-1000 units were installed in parallel with automatic scraping, and operating parameters were adjusted based on LSI / RSI indices.
Results
The Langelier index has been stable at 0–2 and the concentration factor reached up to 5.24, with stable long-term operation. The client repurchased and upgraded the system in 2019.
REQUEST A SOLUTION
Send Us Your Circulating Water Challenge
Share your flow rate, water quality and system type. Our engineers will respond with a selection proposal and ROI estimate within 24 hours.